Project Description
HVAC/BMS controls system for a new Amazon distribution facility. QuestCom worked with HITT, CBRE, and JS Thomas Mechanical Contractors in support of the design and installation of the controls system. QCG was responsible for the receiving, inventory, storage, and installation of all CBRE provided control devices, equipment and wire. QuestCom field crews installed all related equipment, devices, conduit, wire, terminations and commissioning for this project.
Projects Highlights
- Project Location
Jacksonville, Florida - General Contractor
HITT - Mechanical Contractor
JS Thomas Mechanical Contractors - Project Duration
1 Month - Size of Project
$43+ Thousand - Project Details
Design Build Controls System