Project Description
QuestCom provided a design build Mission Critical Power upgrades to the renovated 911 center and the emergency operations center for the Scottsdale Police Department. The project required adding (2) APC 100kva UPS systems to develop a new A and B side power systems throughout the facility. This project required a 3rd UPS (30 kva) to tie in as an additional feed for the emergency operations center and the for the renovated jail cell area. This project required the 911 center to stay up and running during the renovation with minimal down time for critical cutovers to the new equipment. The UPS system backbone included the use of rack mounted ATS switches for single corded devices and new distribution panels and outlets for the A/B requirement.
Projects Highlights
- Project Location
Scottsdale, Arizona - General Contractor
Gruber Industries - Project Duration
6 Months - Size of Project
328+ Thousand - Project Details
Design Build