Project Description
Complete HVAC process controls system for a new tissue machine expansion. QuestCom worked with Haskell, JS Thomas Mechanical, Georgia Pacific, and Jacobs Engineering in support of the design and installation of the highly complex controls system. QCG was responsible for the receiving, inventory, storage, and installation of all GP/Jacobs provided control devices. Once devices were installed into the mechanical and process components QuestCom field crews provided all relate conduit, wire, terminations and commissioning support to the Crossett team.
Projects Highlights
- Project Location
Crossett, Arkansas - General Contractor
Haskell - Mechanical Contractor
JS Thomas Mechanical - Project Duration
12 Months - Size of Project
2.0+ Million - Project Details
Design Build Controls System