February 5, 2026Questcom and APC partnered up for the installation of a new datacenter for the Ak-Chin Indian Community in the County of Maricopa. The new design was an N+1 redundant A and B side systems. The new datacenter included a new APC NetShelter POD with (2) 100kva UPS systems, (2) In row RPP units and (4) In row cooling units. The project included new feeders for the UPS systems, new feeds for the in-row cooling units (both electrically and line sets mechanically), new A and B side distribution panels, and new distribution to the rack level. The design included a phase 2 element for future growth to a second APC NetShelter POD.